Return

Edit Task: DurationOverlap

Format

SCHED / EditTask '<TaskName>' DurationOverlap <DurationOverlap>

Description

The DurationOverlap attribute under EditTask defines the duration of overlap between adjacent assignments for this task. This value is only applicable if DurationIsOverlapRequired is set to true.

Parameters

ParameterDescription
DurationOverlapA double value greater than or equal to zero that defines the task's overlap duration constraint between this task's assignments. The value of the overlap must be equal to this value and if the parameter value is zero then adjacent assignments have neither a gap nor an overlap (before assignmentStop = after assignmentStart).

Examples

Sets the overlap duration to 10s.

SCHED / EditTask 'TaskA' DurationOverlap 10